Sinewave Energy Solutions were engaged to provide high and low voltage services for the customer networks simultaneously across 5 solar farms before the 31st March Deadline. The works included but were not excluded to:

  • Exothermically Welded Earthing Installation and testing for 16 substations
  • High Voltage Terminations and Joints
  • Cable Testing; Sheath and Pressure Testing
  • Protection Commissioning including G59/3 Testing on 13 Mainspro Relays
  • Project Management and Consultancy
  • Senior Authorised Persons for Park Energisation and DNO handovers
  • Procurement of equipment including transformers and Circuit breakers
  • Fall of Potential Testing (FOP) of the entire solar parks earthing system.

 